Summa’s broad experience and capabilities in the manufacturing of high quality control panels and supply of instrumentation for use in municipal water / wastewater process automations systems in addition to strong project management and timely commissioning lead to the successful completion of the project.
The goal of the upgrades was to increase the plant capacity from 45 million LPD (litres per day) to 80 LPD
The Scope of the Project included:
Intricate coordination of work with contractors and owner was required to phase and schedule activities around peak seasonal requirements for water supply
The goal was to deliver on schedule and on budget to meet and exceed the expectations of this major upgrade project – all work conducted under strict compliance to Utilities Kingston Standards
Summa was responsible for manufacturing and commissioning of ten (10) major PLC panels as well as a large number of related local control, analyzer, and communication panels, and the supply and commissioning of process instrumentation
PLC: Rockwell ControlLogix
SCADA: Schneider WonderWare
OIT: Rockwell PanelView
Instrumentation: Summa Supplied